The project included completing the remaining 28 m of the dam height, construction of spillway, access roads, grouting, operating of access tunnel, and water intake structure.
The project was completed in April 2006.
Project Information:
Dam type: Rock-fill with clay-core
Crest level: 1200 m (from sea level)
Dam height: 49 m
Dam crest length: 250 m
Reservoir volume: 17 million m3
Spillway type: Gated in the abutment
Excavation volume: 45.000 m3
Earth-fill volume: 326.000 m3
Concrete Casting: 25.000 m3
Total length of tunnels and galleries: 650 m